Syncline is developing the Berrigan BESS project which will support the local grid and help deliver affordable and reliable power to Southern NSW. From our experience with MREH we have designed a 300 MW 4-hour storage facility. The land is secured and planning and grid process well underway.
The project is planned to connect near the existing Finley Terminal station into both the 132 kV and 66 kV network and the project has a target commissioning date of fourth quarter 2026.